I am attempting to run the HYSPLIT model daily from mid-november to mid-december of the year 2012. How is it possible to input the start and finish date in the GUI?
Thank you in advance.
Daily model between two months
-
- Posts: 660
- Joined: November 7th, 2012, 3:14 pm
- Registered HYSPLIT User: Yes
Re: Daily model between two months
On way to do it is to set up your run to start in mid November and run it until the 30th. Then set up the same run but starting December 1st until your desired en date in December. Make sure you have the meteorological data that span over the period you are interested in.