Page 1 of 1

HYSPLIT running period

Posted: March 21st, 2018, 4:32 am
by jonghun33
I am running HYSPLIT window version.
When i set the total run time 288 hours( 7 days), It work.
But when i set the total run time more than 288 hours, It doesn't work.
attached image is the error log of run time things.

I want to simulate more than 1 month period. What should i have to do to simulate hysplit

plz help me.

Re: HYSPLIT running period

Posted: March 21st, 2018, 6:36 am
by glenn.rolph
You did not provide your CONTROL file but there is a limit of 12 meteorological filenames allowed in the CONTROL file, so you will have to concatenate your meteorological files. Search for concatenate in the forum and you will find similar questions/answers such as:

viewtopic.php?f=10&t=1344&p=3847&hilit= ... nate#p3847
viewtopic.php?f=28&t=1271&p=3569&hilit= ... nate#p3569